Scope of work
- Site
- Bayport Mitigation at Devils Swamp
- Finding
- Polygon B: shrub stem density46.6 stems/m² in Polygon B (field verified), no benchmark in the record
- Vendor
- Date
- Nov 17, 2026
Quantitative vegetation monitoring, transects and stem quadrats in Polygon B.
- The work
- Quantitative vegetation monitoring, transects and stem quadrats
- Where
- Polygon B
- By when
- Not in the record
- Budget guide
- $8,000–$15,000 per surveymodeled
The work
Quantitative vegetation monitoring, transects and stem quadrats
Expected effect: Percent cover by species along fixed transects and rooted shrub stems per square meter by polygon, comparable with earlier years.
Specification
Eco Pass standard template- Quantity and unit
- 1 surveymodeledplaceholder — not sourced
- Area and location
- Polygon B, Not in the record (see the site plan)
- Method
- Percent cover by species in fifteen 1 m² quadrats along each fixed 150-ft transect, and rooted shrub stems counted in five randomly placed 1 m² quadrats per polygon, as in earlier years.
- Site access
- Not in the record
- Site contact
- Not in the record
- Deliverable format
- Signed report (PDF) naming the field lead, the method and the dates of the work
- Raw data as a spreadsheet (CSV or XLSX), one row per sample point
- Photos as JPEG with the date and GPS location embedded
- GIS files (shapefile or GeoJSON) for any area or transect mapped
- Evidence acceptance criteria
- All 4 items under "Evidence required on completion" are received.
- Each reading names who collected it, the method used and the date.
- Photos and GIS files carry their date and location, and fall inside the work area.
- The finding closes when the evidence shows the issue is resolved.
Performance target
No performance target on file for this finding.
Evidence required on completion
- Signed report with method and surveyors
- Transect cover tables
- Shrub stem quadrat counts
- Species list
Budget guideGuide only
$8,000–$15,000 per survey
modeledSource: placeholder — not sourced